OPEN CONTRACTS |
||||
| Job | Point of Contact | Job Description | Contract Amount | Completion |
| USACE MOBILE DISTRICT | IDIQ | 3.5 Million | ||
| Ft. Rucker Office | Design/Repair 4 Bridges |
1,078,383.68 | Nov-10 | |
| Terry.D.Cromer@usace.army.mil | Design/Build Mail Distribution Center | 619,000 | DEC 2010 | |
| NAVFAC SOUTHEAST ROICC GULFPORT |
Okang.Hemmings@navy.mil | Replace Dust Collection System | 382,676 | AUG 2010 |
| TYNDALL 325TH CONS/LGCCA | Joshua.Estevez@tyndall.af.mil | Repair Airfield Drainage | 664,331 | JAN 2011 |
| Ft. Campbell, KY. | regina.skaggs@us.army.mil | Projects: General Construction/BPA. | $25,000-$100,000 | SEP 2008-SEP 2013 |
| Blanket Purchase Agreement | Debra.Rapp@us.army.mil | TASK ORDERS Completed: | ||
| FMIP Equipment | $61,083.00 | |||
| Remove and Replace Fence at Gate 6 | $25,003.82 | |||
| Install Gates and Bollards | $59,628.32 | |||
| PT Equipment | $38,188.65 | |||
| Replace Barrack Mailboxes | $44,196.93 | |||
| Replace Carpet Bldg 6907 & 6908 | $22,859.90 | |||
| Construct Zero Range | $63,480.31 | |||
| Construct Dog Kennel Fence | $30,327.46 | |||
| Replace Basketball Court & Goal | $28,839.93 | |||
| Replace Carpet Bldg 123 & 127 | $27,987.03 | |||
| Improve Gate 1 | $23,974.09 | |||
| BBQ Grills and Pavilions | $59,623.90 | |||
| Install Sidewalks | $34,421.10 | |||
| Construct Rope Climber | $7,187.54 | |||
| Construct PT Equipment | $41,226.04 | |||
| Refinish Hangar Bay Floor | $38,836.08 | |||
| Install Brick Around Helicopter Display | $6,833.44 | |||
| Sidewalks at Gorgas Ave. | $22,672.43 | |||
| Repair SPC Obstacle Course | $67,472.43 | |||
| JOINT VENTURE JOBS: | ||||
| Hollon/Barlovento | Shannon.I.richardson@usage.army.mil | Projects: WEAPONS REPAIR BUILDING | JV 6.3 Million | JAN 2011 |
| USACE Savanna District | ||||
| Ft. Benning Office | ||||
| CH Contracting/Barlovento | Terry.D.Cromer@usace.army.mil | Projects: Cairns Airfield Paving IDIQ | JV 3.5 Million | OCT 2010 |
| USACE Mobile District | ||||
| Ft. Rucker Office | ||||
| CH Contracting /Barlovento | Projects: Camp Rudder Firestation | JV 1 Million | OCT 2010 | |
| Eglin DOC | ||||
COMPLETED CONTRACTS |
||||
| Ft. Campbell, KY. | lilia.wood@us.army.mil | Projects: General Construction. | $0.00-$25,000.000 | |
| Blanket Purchase Agreement | Task Order: Construct Rope Climb | |||
| Supply Facility at Hanchey Field | Gary German | Construct Supply Facility at Hanchey Field. Work | $336,000.00 | 2/09 |
| Ft. Rucker, AL | Phone: 334-685-2318 | includes saw cutting 3,500 linear feet of existing | ||
| Contract No.: W911SE-07-D0 | garyg.@lakeshoreeng.com | concrete, removing from Air Field and installing new | ||
| 0040-0032-003 | foundation for 6,000 sq.ft. building. Erecting metal | |||
| building, all interior and exterior finishes, fire | ||||
| protection, plumbing and electrical, acoustical ceilings, | ||||
| bathrooms, offices and flooring. | ||||
| Navy Support Facility | Charlene Buduo | Domestic Water Line Replacement, Bldg. 350, located at | $400,000.00 | COMPLETED MARCH 09 |
| Panama City, FL | Phone: 850-636-6339 | Naval Support Activity, Panama City Beach, FL | ||
| Contract No: N69458-08-R-6072 | Contract Specialist | |||
| charlene.buduo@navy.mil | ||||
| Department of Veterans Affairs | Jerry Watts | Demolition work to remove and replace concrete side- | $228,000.00 | 10/07 |
| VA Hospital - Birmingham, AL | Phone: 205-554-4639 | walks and service entrances at the VA Medical Center | ||
| Contract No. VA247-C-0122 | Fax: 478-274-5610 | Building. | ||
| Jerry.Watts@VA.Gov | ||||
| Fuel Pier @ Hurlbert Field | Gerald Morris | Repaired & painted fuel line, repair HVAC installation, | $63,000.00 | 10/07 - 11/07 |
| Ft. Walton Beach, FL | Phone: 850-362-0284 | replaced damaged flooring, installed railings & bath | ||
| Contract No. W91278-04-C-0032 | Fax: 850-362-0289 | fixtures, added bollards, installed concrete walks and | ||
| Gerald@morris/Clark.com | drives. | |||
| Picerne Military Housing | Angela Ray | Painted residential units, repaired and replacements of | $120,000.00 | 5/06 - 11/06 |
| Ft. Rucker Army Base | Phone: 334-503-3600 | electrica switches & outlets. Replacement of door units, | ||
| Daleville, AL | Fax: 334-503-3620 | ceramic tile, all hardware & lighting. Responsible for | ||
| Contract No. F-106-OH0004 | Aray@picernemh.com | locating & removing other materials throughout empty | ||
| multi-unit housing for future use. | ||||
| Wiregrass Habitat for Humanity/ | Elizabeth Tiller | Opray Winfrey's Angel Network in conjunction with | $700,000.00 | 7/06 - 12/06 |
| Oprah Angel Network | Phone: 334-792-8453 | Habitat for Humanity International headed the program | ||
| MS, LA, TX Gulf Coast Regions | Fax: 334-678-7361 | which placed Hollon Homes, LLC in charge of | ||
| Affected by Hurricane Katrina | Etiller@wiregrasshabitat.org | construction of two traditional residential homes & 22 | ||
| Contract No. N/A | modular homes subdivision. Served as Project Manager | |||
| for the entire project. | ||||
| Wiregrass Habitat for Humanity/ | Giovonni Taylor-Peace | After successfully completing first contract of modular | 220,000.00 | 1/07 - 12/07 |
| Oprah Angel Network | Phone: 800-422-4828 | construction for Habitat in Dothan, AL, Hollon | ||
| MS, LA TX Gulf Coast Regions | Gtaylor@habitat.org | Contracting was requested to oversee construction | ||
| Affected by Hurricane Katrina | Gtaylor@habitat.org | management in the Gulf Coast Affected Regions, Hollon | ||
| Contract No. OHD | Homes became Modular Consultant & Project Manager | |||
| for 10 Affiliates. | ||||
| Oprah Angel Network/ | Gregg Sherkin | Oprah's Ange Network's director requested Hollon | $100,000.00 | 11/07 - 2/08 |
| Wiregrass Habitat | Phone: 312-633-1533 | Contracting to oversee their interest in a community | ||
| Diamond Grove Subdivision | Gshirkens@harpo.com | Park to be donated to Wiregrass Habitat for Humanity. | ||
| Dothan, AL | Duties included all concrete sidewalks, the concrete | |||
| Contract No.: N/A | pavilion, sprinkler system & utility placement to supply | |||
| the park. Hollon Contracting also performed all land- | ||||
| scaping, the placement of all exercise equipment and | ||||
| pavilion canopy to be supplied. | ||||